Use the values in the table to calculate activity durations and variances for the project below, an app for the Lindsey Wilson bookstore. Using the critical path method (CPM), what is the project critical path and likely duration of the project? Create an activity-on-node (AON) diagram. Where is the slack (if any) to “crash” the project if necessary? Why is this process important for a project manager to successfully manage the project?
Activity | Expected Duration | Predecessors |
A | 5 days | — |
B | 6 days | A |
C | 2 days | A |
D | 4 days | A |
E | 6 days | B, C |
F | 6 days | D, E |
G | 12 days | F |
H | 4 days | G |
I | 6 days | F |
J | 7 days | H, I |
Please write a 300-to-500 word paper in APA Style answering all questions, and include at least 2 reputable sources.
• 12-pt. Times New Roman font, Double-spaced and 1” margins on all pages.
• Please provide a title page including your Name, Course Number, Date of Submission, and Assignment name.
• Paraphrasing of content – Demonstrate that you understand the case by summarizing the case in your own words. Direct quotes should be used minimally.